| The City of Roseville 2013 |
The City of Roseville 2013 Micro Surfacing of Major Collectors & Arterials. The project scope included work on major collectors and arterials for the City of Roseville, CA. This included 8” asphalt dig outs 4k tons, removal of all existing striping, 75 traffic loops, placement of Micro Surfacing using Type Two aggregate gradations (3,900 wet tons placed). This project required all work on collectors and arterials to be performed at night. Upon completion all striping was replaced with thermo plastic striping. Post Picture is one of the major intersection that log an average (120 ADT). All Micro Surfacing work was performed using truck mounted Pavers. All traffic lanes were required to be opened by 6am. No late re-openings.
Work done by ISSA Member TELFER Highway Technologies |